Where Are They Now? -- A Look at Current Oakland Residential Construction (UPDATED: March 31)

In the past two weeks, the Oakland Conduit looked into the current progress of some of the largest residential real estate developments currently under construction in Oakland. We compiled information from the planning department and developers, and took pictures of the individual sites. This is what we found, complete with recent updates: 

4901 Broadway “Baxter on Broadway”

Currently (Photo Credit: Sam Felsing) 

 1409_Broadway_1.JPG1409_Broadway_5.JPG

When Completed (Photo Credit: SRM Development/Oakland Planning Commission)

4901_Broadway_(7).png4901_Broadway_(6).png

Developer:  SRM Development

Units: 130 residential units (126 apartments, 4 town homes); ground floor commercial space

Construction Start Date: Late 2015

Expected Completion Date: First Quarter of 2018

How to Apply to Live Here:  The managing company will set up a website for applicants likely in January of 2018.

Move In Date:  Targeted for April 2018

Developer Hopes for the Project:

 “Our project will be providing the tenants with on-trend amenities such as secured bike storage, dog wash & run, electric vehicle charging stations along with residential roof deck with adjacent indoor lounge and individual unit balconies which we hope will attract applicants to the area. In addition, we will be improving upon the neighborhood visually. The preexisting buildings on the lot were very old, rundown and unsafe. Our project will bring new life to the surrounding neighborhood by providing an updated building and making it more visually pleasing” –Leslie Larson, Marketing Coordinator at SRM Development

Brooklyn Basin

Current Status (Photo Credit: Sam Felsing) 

 Brooklyn_Basin_1.JPGBrookly_Basin.JPG

When Completed (Photo Credit: Signature Development Group)

 Brooklyn_Basin_1.jpgBrooklyn_Basin_2.jpg

Developer: Signature Development Group, Zarsion America, Reynolds & Brown, and Signature Homes

Units: 3,100 residential units including 465 affordable housing units; 200,000 square feet of ground-floor commercial space; minimum of 3,950 parking spaces; 32 acres of parks and public open space; two renovated marinas (total 170 boat slips); existing wetlands restoration area

Construction Start Date: The first structure, Parcel B “Terrace Apartments” (241 residential units; see above photo), is set for April 2017

Expected Completion Date: Parcel B is estimated to be complete in late 2018-early 2019

Developer Hopes for the Project:

“Brooklyn Basin is about bringing the waterfront back in Oakland, and creating a new neighborhood that involves that waterfront and involves the historic center of the town and involves bringing people to and from those places” –Mike Ghielmetti, President Signature Development Group (via the www.brooklynbasin.com website)

1640 Broadway "44Seven" (Updated: March 31)

Currently (Photo Credit: Megan Collins)

1640_Broadway_3.JPG1640_Broadway_4.JPG 

When Completed (Photo Credit: Lennar Corporation/Solomon Cordwell Buenz)

 1640_Broadway_6.PNG1640_Broadway_7.PNG

Developer:  Lennar Multifamily Communities

Units: 254 multi-family units (mix of studio, 1, 2 and 3-BR); approximately 5,000 square feet of ground-floor commercial space for general retail and/or restaurant uses; off-street parking for 232 cars and 66 bicycles

Construction Start Date: February 2017

Expected Completion Date: First homes will be delivered in January 2019, and final homes delivered in April 2019.

How to Apply to Live Here:  Prospective occupants and residents can access floor plans and apply for leases once the website, 44Seven.com, becomes live in November 2018.

Move In Date: First move-ins are targeted for January 2019.

Developer Hopes for the Project: 

"44Seven is turning a page in the story of Oakland, pioneering a new, exceptional standard of living while honoring the city’s artful, charismatic character. It’s a place where one can enjoy a modern, elevated lifestyle without sacrificing the neighborhood vibe, urban edge or individual expression.

At 44Seven, home will extend beyond your four walls of the building to the block with your favorite café and laid-back neighborhood bar. It is everything urban living aspires to be: connected and engaging yet casual and comfortable. It allows big-city living to feel small in the best possible way. 44Seven is the quintessential example of what being at the center of it all can bring to your life: more time with friends and loved ones and more time soaking up culture, art, music and entertainment. 

Amidst the familiar signs of urban renewal, 44Seven isn’t rewriting the Oakland story. It’s simply adding a new chapter. It’s an emblem of both the city’s storied past and its vibrant future, where the keys to home are also the keys to a new frontier, to all that is Oakland." -Lindsey Bernhardt, Account Manager at LinnellTaylor Marketing

2302 Valdez “Alta Waverly”

Currently (Photo Credit: Sam Felsing)

 2302_Valdez_1.JPG2302_Valdez_2.JPG

When Completed (Photo Credit: Wood Partners/PYATOK)

 2302_Valdez_3.jpg2302_Valdez_4.jpg

Developer: Wood Partners, Carlyle Group

Units: 196 apartments; 31,500 square feet of retail space

Construction Start Date: Early 2016

2400 Valdez

Currently (Photo Credit: Sam Felsing)

 2400_Valdez_1.JPG2400_Valdez_3.JPG

When Completed (Photo Credit: The Hanover Company/Oakland Planning Commission)

 2400_Valdez_2.PNG2400_Valdez_4.PNG

Developer: The Hanover Company

Units: 224 residential units; 23,000 square feet of retail space

Construction Start Date: Late 2016

How to Apply to Live Here: Contact Lockehouse Retail Group, inc. for commercial leases 

1700 Webster St

Currently (Photo Credit: Sam Felsing)

1700_Webster_1.JPG1700_Webster_3.JPG 

When Completed (Photo Credit: Gerding Edlen/Oakland Planning Commission)

1700_Webster_2.png1700_Webster_4.png 

Developer: Gerding Edlen

Units: 206 units; 6,000 square feet of retail/restaurant space; 206 parking spaces

Construction Start Date: Demolition was completed in December 2016; and the site was cleared March 2017

459 8th St 

Currently (Photo Credit: Megan Collins)

 459_8th_1.JPG459_8th_3.JPG

When Completed (Photo Credit: YHLA Architects/Oakland City Council)

459_8th_2.png 459_8th_4.jpg

Developer: Saint Regis Properties

Units: 50 housing units; 4,000 square feet of retail space

Construction Start Date: Mid-2016 

250 17th St “Alice Street Apartments"

Currently (Photo Credit: Megan Collins)

250_17th_1.jpg 250_17th_2.JPG

When Completed (Photo Credit: Kotas/Pantaleoni Architects)

 250_17th_3.jpg

Developer: Simeon Properties

Units: 74 units (52 1-BR, 15 2-BR, 7 studios)

Construction Start Date: Unknown, but currently under construction 

Expected Completion Date: 2018

4801 Shattuck Ave

 4801_Shattuck_4.JPG4801_Shattuck_3.JPG

When Completed (Photo Credit: Nautilus Group)

4801_Shattuck_1.jpg4801_Shattuck_2.jpg 

Developer: Nautilus Group 

Units: 42 units (studio, 1-BR, 2-BR); ground-floor commercial space

Construction Start Date: Unknown, but currently under construction

9400 International

Current Status--As of January 2017 (Photo Credit: Mark Hedin/Bay Area News Group)

9400_International_1.jpg 

When Completed (Photo Credit: Related California)

 9400_International_2.jpg

Developer: Related California, Acts Full Gospel Church

Units: 59 affordable housing units (18 1-BR, 23 2-BR, 18 3-BR); 3,500 square feet of retail space 

Construction Start Date: Unknown, but currently under construction

Expected Completion Date: August 2017

612 18th St “The Jefferson”

Current Status (Photo Credit: Megan Collins)

 612_18th_1.JPG612_18th_3.JPG

When Completed (Photo Credit:Bay West Development/Kahn Design Associates)

 612_18th_2.jpg612_18th_4.jpg

Developer: Bay West Development

Units: 80 units; ground floor retail space

Construction Start Date: November 2015

Expected Completion Date: July 2017

2935 Telegraph Ave “Courthouse Condominiums” (Updated: March 31)

Current Status (Photo Credit: Sam Felsing)

 2935_Telegraph_1.JPG2935_Telegraph_3.JPG

When Completed (Photo Credit: Madison Park Financial Corporation)

2935_Telegraph_2.jpg2935_Telegraph_4.jpg 

Developer:  Madison Park Financial Corporation

Units: 162 residential units; 2,045 square feet of retail space

Construction Start Date: Unknown, but currently under construction

Expected Completion Date: October 2017

How to Apply to Live Here:  The managing company will set up a website for applicants likely in April or May 2017

Move In Date:  October 2017

Developer Hopes for the Project:

"Besides the obvious initial impact of replacing a blighted vacant lot on a busy thoroughfare with a brand new development, the addition of 162 market rate units will provide much needed housing in a severely supply constrained market and energize existing retail in the area. The 2 new retail spaces, one of which will most likely be a restaurant, will tie the neighborhood in with the Uptown/KONO corridor and increase activity in the area further stimulating the local retail businesses." -Bob Huff, Project Manager at Madison Park Financial Corporation